FILMPORT UPDATE November 7, 2006

Many people have been asking about progress at FILMPORT. Here’s an update:
-
Work started on August 30th. Site preparation is nearly complete.
-
TEDCO is presently excavating and cleaning up contaminated areas of the site. This work will continue through November.
-
Pile driving for the deep foundations will commence on November 20th once TEDCO clean-up crews are out of the way.
-
Foundation work will continue through the Winter months. The erection of steel structures will begin in early Spring, with concrete wall and roof sections following in late Spring.
-
Some sound stages should be ready for occupancy by December, 2007. All of Phase 1 will be ready for occupancy by Spring 2008.